KUKL PID WORK PROGRESS

WORK PROGRESS SUMMARY
BDS: 49.94 km out of 60.6 km
DNI: 612.80 km out of 670 km

 Package: BDS 1

MahankalChour Chowk to Chabahil Chowk
Today: 10 m To Date: 835.9 m Total: 909 m
Pipe Diameter: 1400 mm

Chabahl Chowk to Narayangopal Chowk
Today: 55 m To Date: 2538.5 m Total: 2922 m
Pipe Diameter: 1400 mm

Narayangopal Chowk to Bansbari SRT
Today: 12 m To Date: 1118 m Total: 1786 m
Pipe Diameter: 1000 mm

Chabahil Chowk to Gausala Chowk
Today: 5 m To Date: 975 m Total: 1193 m
Pipe Diameter: 1000 mm

Khasi Bazar Kalanki to Sita Petrol Pump Ring Road
Today: 0 m To Date: 53 m Total: 250 m
Pipe Diameter: 700 mm

Sita Petrol Pump Ring Road to Balkhu Chowk
Today: 0 m To Date: 781 m Total: 950 m
Pipe Diameter: 400 mm

Ekanta Kuna Ring Road to Talchhikhel Chowk Ring Road
Today: 0 m To Date: 1788.5 m Total: 1882 m
Pipe Diameter: 400 mm